Newport High School

Bellevue, WA

Work In Progress

Showing Phase 2 of Project, as of Dec 2023.

Phase 2 installing ½” Securock substrate board to the last section of high roof, previous sections and mid-roof complete thru torch down vapor barrier. PVC and walk-pad are complete.

Project: Newport High School, Building Reroof

Location: Bellevue, WA 98006

Customer: Cornerstone General Contractors

Scope of Work: Newport High School Modernization & Additions is a 3-phase project. Phase 1 roof work was completed in April 2023. Phase 2 to be complete Feb/Mar 2024. Phase 3 is currently scheduled to be completed by Dec ‘24/Jan 25’.

PM: John Vanderhoof

PX: Mike Trout

Supt: Dave Wetherbee

Anticipated completion: January 2025

All 3 Phases Include:

  • 873 sq R38 with Duro-Tuff 60mil PVC in light gray – attachment via Induction welding

  • 75 sq Hydrotech Hot Rubber, R40 w/pavers, and green roof

  • 15 sq Soprema SBS 2-ply tie-in at existing

Phase 1 Includes:

  • 0597 – Phase 1 PVC complete prior to Solar Array install

  • Badger & Moore – Phase 1 installing ½” Securock substrate board & torch down vapor barrier

Phase 2 Includes:

  • 0946 – Phase 2 installing ½” Securock substrate board