Showing Phase 2 of Project, as of Dec 2023.
Phase 2 installing ½” Securock substrate board to the last section of high roof, previous sections and mid-roof complete thru torch down vapor barrier. PVC and walk-pad are complete.
Project: Newport High School, Building Reroof
Location: Bellevue, WA 98006
Customer: Cornerstone General Contractors
Scope of Work: Newport High School Modernization & Additions is a 3-phase project. Phase 1 roof work was completed in April 2023. Phase 2 to be complete Feb/Mar 2024. Phase 3 is currently scheduled to be completed by Dec ‘24/Jan 25’.
PM: John Vanderhoof
PX: Mike Trout
Supt: Dave Wetherbee
Anticipated completion: January 2025
All 3 Phases Include:
873 sq R38 with Duro-Tuff 60mil PVC in light gray – attachment via Induction welding
75 sq Hydrotech Hot Rubber, R40 w/pavers, and green roof
15 sq Soprema SBS 2-ply tie-in at existing
Phase 1 Includes:
0597 – Phase 1 PVC complete prior to Solar Array install
Badger & Moore – Phase 1 installing ½” Securock substrate board & torch down vapor barrier
Phase 2 Includes:
0946 – Phase 2 installing ½” Securock substrate board